A Farmer's Share · Build Tracker · Provender Demo MVP + v2 Roadmap
27/181
Demo Tasks
5
In Progress
15%
Demo %
0/48
v2 Tasks
0/18
Deps Done
Jun 1
Launch
DEMO PATH PROGRESS (v1 + cross-cutting)15% complete · 27 of 181 tasks
★ THREE MOMENTS THAT MAKE THE DEMO
Pin click → detail panel (t23). Community Wealth Score moves on filter (t24). Compliance gap callout visible (t25). If only these three work perfectly, the demo works.
v1 — Demo MVP (Jun 1)
Click a phase to expand groups. Click any status pill to cycle: Open → In Progress → Done → Blocked.
Phase 0Foundation & EnvironmentApr 28May 4
12/26
Phase 1Entry & Auth FlowMay 5May 9
5/26
Phase 2Map & System TabMay 10May 18
0/20
Phase 3Territory TabMay 19May 23
0/9
Phase 4Flow TabMay 21May 26
0/10
Phase 5Ground Tab & Locked FieldsMay 24May 28
0/10
Phase 6Demo Mode & QAMay 26May 30
1/14
Phase 7Pre-Launch OperationsMay 29Jun 1
2/17
PivotAtlas Pivot — May 2026May 19May 19
7/18
Cross-Cutting Work
Disciplines that run throughout the build. Touches every phase.
Cross-CuttingCross-Cutting Work
0/31
A FARMER'S SHARE CORPORATION · PUBLIC BENEFIT CORPORATION · MAMARONECK, NY·Provender Demo MVP · Target launch Jun 1, 2026 · Updated with full advisor input + structural audit